Microsoft agrees to $2.5M settlement over Leesburg Data Center emissions - WFXRtv

During a power outage caused by substation failure, the Leesburg Data Center operated 62 emergency engines that exceeded permitted emissions limits for NOx, CO, VOC, PM10, and PM2.5, affecting air quality for nearby residents.

Date it happened
2025-06-27
Organisation involved
Microsoft
Where this came from
Share this incident
XLinkedInFacebookWhatsAppEmail
Attribution

This incident was imported from WFXRtv. Our additions to it — the structured fields, the translation, the checks against other reports — are published under the same licence.

This is a record of what was reported, not a finding that anyone broke the law. If it names your organisation and you believe it is wrong, the corrections process is free and open to everyone.

Microsoft agrees to $2.5M settlement over Leesburg Data Center emissions - WFXRtv — Wayward Fowl